Download or read book Major Projects Report 2008 written by Great Britain. National Audit Office and published by The Stationery Office. This book was released on 2008 with total page 224 pages. Available in PDF, EPUB and Kindle. Book excerpt: A companion work to the main report (HCP 64-I).
Download or read book The Major Projects Report 2009 written by Great Britain. National Audit Office and published by The Stationery Office. This book was released on 2009 with total page 44 pages. Available in PDF, EPUB and Kindle. Book excerpt: The current defence programme is unaffordable. The Ministry of Defence (MOD) has already reduced the deficit between the defence budget and planned expenditure by £15 billion, but a shortfall of between £6 billion and £36 billion remains. The financial crisis means a substantial increase in funding is unlikely, and closing the gap will require bold action as part of the Strategic Defence Review which is expected after the General Election. The MOD has reduced equipment numbers being bought on some projects and taken short-term decisions to slip other projects, but this approach will lead to long-term cost increases. In 2008-09, costs on the 15 major defence projects examined by the NAO increased by £1.2 billion, with two thirds (£733 million) directly due to the decision to slow projects. This approach does not address the fundamental affordability problems, increases through-life costs and represents poor value for money on the specific projects affected. There are signs of improvement in project cost control with innovative decisions being taken to ensure progress but unless the MOD addresses the underlying budgetary and governance issues it will not consistently deliver value for money nor will the operational benefits of expensive new capabilities be available to the Armed Forces in a timely manner or in the numbers originally planned. The current cost of 15 major military projects has risen by £3.6 billion, compared with the expected costs when the investment decisions were taken. The total slippage, averaged over the 14 major projects with in service dates, is over two years per project.
Download or read book Major projects report 2007 written by Great Britain: National Audit Office and published by The Stationery Office. This book was released on 2007-11-30 with total page 40 pages. Available in PDF, EPUB and Kindle. Book excerpt: The Major Projects Report 2007 covers cost, time and performance data for military equipment projects in the year ended 31 March 2007. 20 of the largest projects are examined where the main investment decision has been taken by the Ministry of Defence (the MoD), along with ten projects still in the Assessment Phase. Overall the MoD is in a similar position to 2006 for forecast cost and performance, but there continue to be time delays. The current total forecast cost for the 20 largest projects is £28 billion, which is £2.5 billion over the 'most likely' budget when the main investment decision was taken. The MoD expects ten projects to deliver within their most likely budgeted cost. Most of this cost growth occurred in earlier years but, on two projects, the Type 45 Destroyer (£354 million) and the Astute Class Submarine (£142 million), there has been significant cost growth in-year. The MoD has now agreed revised contracts on both of these projects to incentivise industry to reduce costs. The MoD was again pro-active in limiting potential in-year cost increases on individual projects through reassessing requirements, reducing quantities of equipments and re-allocating expenditure to other projects or budget lines. Five projects were delayed by a total of an extra 38 months this year. Of these, the most significant were the Type 45 Destroyer which has been delayed by a further 11 months and the Terrier and Next Generation Light Anti-Armour Weapon projects have each been delayed by a further 12 months. Detailed Summary Sheets for each of the 30 Projects are in Volume 2 (HCP 98-II, ISBN 9780102951493). There have been significant developments of interest on a project that appeared in the Major Projects Report until 2002-03, the Landing Ship Dock (Auxiliary) project, and detailed findings are given in Volume 3 (HCP 98-III, ISBN 9780102951509).
Download or read book A Nuclear Weapons Free World written by Nick Ritchie and published by Springer. This book was released on 2012-10-29 with total page 244 pages. Available in PDF, EPUB and Kindle. Book excerpt: President Obama and the UK Labour and Coalition governments have all backed the renewed momentum for serious progress towards a world free of nuclear weapons, whilst the UK finds itself embarked on a controversial and expensive programme to renew its Trident nuclear weapons system. What does the UK process tell about the prospects for disarmament?
Download or read book Ministry of Defence written by Great Britain: Parliament: House of Commons: Committee of Public Accounts and published by The Stationery Office. This book was released on 2009 with total page 40 pages. Available in PDF, EPUB and Kindle. Book excerpt: The Major Projects Report 2008 provides information on the time, cost and performance of 20 of the largest military equipment projects being undertaken by the Ministry of Defence, where the main investment decision has been taken, as well as the top 10 projects in the earlier Assessment Phase. In the last year, the 20 biggest projects suffered a further £205 million of cost increases, and 96 months additional slippage. This is the worst in-year slippage since 2003. The total forecast costs for these projects have now risen to nearly £28 billion, some 12 per cent over budget. Total slippage stands at over 40 years, a 36 per cent increase on approved timescales. The number of Key User Requirements reported as being "at risk" of not being met has also increased from 12 to 16 in the last year. This is a disappointing set of results, particularly because the problems are being caused by previously identified failures such as poor project management, a lack of realism, not identifying key dependencies and underestimating of costs and timescales. The reoccurrence of these problems suggests that the Department's latest acquisition reforms, introduced in 2001, are not yet resulting in the Department making better investment decisions or improving the execution of its defence projects. Project delays also have a detrimental impact on operational capability and costs, in some cases forcing the Department to buy interim vehicles and continue using equipment suffering from obsolescence in Afghanistan and either older Hercules aircraft will have to serve beyond their planned out of service date, or other transport aircraft will have to be bought or leased to address a growing gap in capability.
Download or read book Cost Engineering Health Check written by Dale Shermon and published by Taylor & Francis. This book was released on 2016-11-03 with total page 197 pages. Available in PDF, EPUB and Kindle. Book excerpt: High quality cost estimating gives a business leader confidence to make rational financial decisions. Whether you are a business leader or a cost estimating manager, you have a vested interest in understanding whether you can depend on your organisation's ability to generate accurate cost forecasts and estimates. But how can business leaders have confidence that the cost information that they are being provided with is of high quality? How can a cost estimating manager be sure that their team is providing high quality cost information? QinetiQ's Cost Engineering Health Check is used as a capability benchmarking tool to identify improvement opportunities within their clients' cost estimating capability, enabling them to focus on areas that have the potential to increase their competitiveness. High quality estimating leads to accurate budgets, a reduced potential for cost growth, accurate evaluation of risk exposure, and the opportunity to implement effective earned value management (EVM). The Cost Engineering Health Check employs a standardised competency framework that considers all aspects of cost estimating capability, and provides an objective assessment against both best practice and the industry standard. This framework is based on QinetiQ's long established, tried and tested, Knowledge Based Estimating (KBE) philosophy comprising Data, Tools, People and Process, with additional consideration given to cultural and stakeholder assessments.
Download or read book Defence Equipment 2009 written by Great Britain. Parliament. House of Commons. Defence Committee and published by The Stationery Office. This book was released on 2009 with total page 212 pages. Available in PDF, EPUB and Kindle. Book excerpt: The mission of the MoD's (Ministry of Defence's) Defence Equipment and Support (DE & S) organisation is to equip and support our Armed Forces for operations now and in the future. Support to current operations in Afghanistan and Iraq has taken priority and the organisation has performed well. The Urgent Operational Requirement (UOR) system remains highly effective in enabling vital equipment to be provided quickly to the two theatres to meet rapidly changing threats, but there are concerns that UORs represent a partial failure to equip our forces for predicted expeditionary operations, and on their effects on the core budget in future years. DE & S' performance in procuring longer-term equipment declined significantly in 2007-08. The forecast costs for the 20 largest defence projects increased by £205 million and the forecast delays increased by some 100 months in the year. The improvements promised by both the long-standing application of the principles of 'smart procurement' and the more recent formation of the DE & S organisation appear not to have materialised. The FRES (Future Rapid Effect System) programme has been a fiasco, being poorly conceived and managed from the outset. The Committee condemns the failure to date to publish an updated version of the Defence Industrial Strategy and considers that its continuing absence increases the risk that the UK Defence Industrial Base will not be able to meet the future requirements of our Armed Forces. Finally, the UK's future military capability depends on the investment made today in Research and Development. Sufficient funding for defence research needs to be ring-fenced and the MoD must recognise the very high priority of research and reverse the recent cut in research spending.
Download or read book The Economics of Defence Policy written by Keith Hartley and published by Routledge. This book was released on 2012-07-26 with total page 322 pages. Available in PDF, EPUB and Kindle. Book excerpt: Defence policy is of continuing interest and concern to all nations. There are armed conflicts and new threats. Difficult choices cannot be avoided. This book has three aims. First, to identify the typical questions raised by economists when studying defence policy. Second, to show how simple economic analysis can be used to answer these questions and contribute to our understanding of defence issues. Third, to provide a critical evaluation of defence policy.
Download or read book The major projects report 2010 written by Great Britain: National Audit Office and published by The Stationery Office. This book was released on 2010-10-15 with total page 64 pages. Available in PDF, EPUB and Kindle. Book excerpt: Central departmental decisions by the Ministry of Defence to try to balance the defence budget have reduced its cash-flow requirements in the short-term but at a long-term cost that represents poor value for money for the taxpayer. Not making realistic budgetary provision for all likely project outcomes and slowing down projects has resulted in a £3.3 billion increase in a single year, 2009-10, in the total cost of the 15 largest defence equipment projects. For the second successive year the cost performance on the majority of projects has been broadly stable and the rate of timescale slippage has also reduced significantly since last year and 98 per cent of Key Performance Indicators are expected to be met. The MOD did not make realistic budgetary provision for all potential costs, for example, on the Typhoon combat aircraft where the Department decided that it needed to spend £2.7 billion on the programme including the purchase of 16 additional aircraft to meet contractual agreements. It has slowed down projects such as the Queen Elizabeth Class aircraft carriers, leading to further project cost growth of £650 million. And, to address cost overruns, the Department has also reduced the number of items, and therefore capability, to be procured. The MOD recently undertook to report annually to Parliament on the affordability of its ten-year equipment plan, which should help deter the corporate practices which have adverse value for money implications.
Download or read book The major projects report 2011 written by Great Britain: National Audit Office and published by The Stationery Office. This book was released on 2011-11-16 with total page 328 pages. Available in PDF, EPUB and Kindle. Book excerpt: This is a companion volume to the main report (HC 1520-I, ISBN 9780102976786)
Download or read book The Major Projects Report 2012 written by Great Britain: National Audit Office and published by The Stationery Office. This book was released on 2013-01-10 with total page 412 pages. Available in PDF, EPUB and Kindle. Book excerpt: In respect of its largest defence projects there are early signs that the Ministry of Defence has begun to make realistic trade-offs between cost, time, technical requirements and the amount of equipment to be purchased. Nevertheless, the continuing variances to cost and time show the MOD needs to do consistently better. This report, which gives a progress review of the 16 largest defence projects, shows that in the last year there has been a total forecast slippage of 139 months and increase in costs of £468 million. This means that, since the projects were approved, costs have increased by £6.6 billion (around 12 per cent more than the planned cost) and the projects have been delayed by 468 months, taking almost a third longer than originally expected. It would be unrealistic to expect MOD and industry to identify every risk at the start of technically challenging projects. However, the continuing problems indicate that MOD has more to learn from historic. The MOD is accepting the capability risk and some wider costs resulting from these project delays and is having to make difficult decisions about long-term capabilities. The MOD has made a significant investment in new and upgraded helicopters to address the shortfall identified in the NAO's 2004 report. The MOD has also spent £787 million on air transport and air-to-air refuelling aircraft to support current operations and address capability gaps, such as those caused by the previously reported delays to the A400M transport aircraft. However, capability gaps remain
Download or read book Planning for homes written by Great Britain: Parliament: House of Commons: Committee of Public Accounts and published by The Stationery Office. This book was released on 2009-07-02 with total page 40 pages. Available in PDF, EPUB and Kindle. Book excerpt: Housing developments require the approval of planning applications by local planning authorities (Authorities) before they can proceed. The Department for Communities and Local Government has implemented a number of measures in recent years to improve the performance of the development management stage of the planning process, in which applications are considered by Authorities, and to boost planning capacity. The measures include the setting of national targets for the speed of Authority decision-making, and the allocation of £68 million a year in Planning Delivery Grant (the Grant) to Authorities as a reward for meeting targets. The Grant, together with the setting of a 13 week target for decisions, has provided Authorities with an incentive to determine applications more quickly. Between 2002-03 and 2007-08, the percentage of major residential planning applications decided within 13 weeks almost doubled to 67 per cent. The Department's measures to improve the application process have met with mixed success. The Department has encouraged Authorities to hold pre-application discussions with developers, but there is a lack of clarity across Authorities about the purpose of these discussions. Some Authorities have not deployed sufficiently senior and experienced staff in the discussions, and Authorities have also taken different approaches to charging. Authorities' monitoring of developers' discharge of the conditions attached to planning permissions has been given a low priority, partly because of the focus on meeting the 13 week decision target. Authorities have spent about 95 per cent of Planning Delivery Grant on their planning functions, although the extent to which it has resulted in extra expenditure on planning is unclear.
Download or read book The Project Risk Maturity Model written by Martin Hopkinson and published by Taylor & Francis. This book was released on 2017-03-02 with total page 265 pages. Available in PDF, EPUB and Kindle. Book excerpt: Top businesses recognise risk management as a core feature of their project management process and approach to the governance of projects. However, a mature risk management process is required in order to realise its benefits; one that takes into account the design and implementation of the process and the skills, experience and culture of the people who use it. To be mature in the way you manage risk you need an accepted framework to assess your risk management maturity, allowing you to benchmark against a recognised standard. A structured pathway for improvement is also needed, not just telling you where you are now, but describing the steps required to reach the next level. The Project Risk Maturity Model detailed here provides such an assessment framework and development pathway. It can be used to benchmark your project risk processes and support the introduction of effective in-house project risk management. Using this model, implementation and improvement of project risk management can be managed effectively to ensure that the expected benefits are achieved in a way that is appropriate to the needs of each organisation. Martin Hopkinson has developed The Project Risk Maturity Model into a robust framework, and this book allows you to access and apply his insights and experience. A key feature is a downloadable resource containing a working copy of the QinetiQ Project Risk Maturity Model (RMM). This will enable you to undertake maturity assessments for as many projects as you choose. The RMM has been proven over a period of 10 years, with at least 250 maturity assessments on projects and programmes with a total value exceeding £60 billion. A case study in the book demonstrates how it has been used to deliver significant and measurable benefits to the performance of major projects.
Download or read book Renewing the physical infrastructure of English further education colleges written by Great Britain: Parliament: House of Commons: Committee of Public Accounts and published by The Stationery Office. This book was released on 2009-07-28 with total page 52 pages. Available in PDF, EPUB and Kindle. Book excerpt: In 2001, the newly established Learning and Skills Council (the Council) took over a programme of capital works in the further education sector, to renew an estate that was too large, with much of it in poor condition and no longer fit for modern educational purposes. By March 2008, a total of £4.2 billion of projects had been approved 'in detail', including grant support from the Council of £1.7 billion, and about half of the estate had been renewed. Since April 2008, there has been a very serious failure in the management of the programme. It approved 'in principle' 79 colleges' projects, which required nearly £2.7 billion of Council funding more than it could afford. Before the current problems arose, the programme had achieved some successes, enabling the estate to be reduced in size, and the buildings are generally of good quality and are contributing to increased learner participation. The economic downturn could affect colleges' ability to fund projects by restricting their access to loan finance or their ability to sell surplus assets. The indebtedness of the sector is rising. The Council needs to monitor closely the financial health of some colleges, particularly those that have borrowings that exceed 40 per cent of their annual income. In 2010, the Council is expected to be dissolved and its functions taken over by the Skills Funding Agency and the Young People's Learning Agency. There needs to be clarity about responsibilities for the capital programme, and additional administrative burdens on colleges must be avoided.
Download or read book NHS pay modernisation in England written by Great Britain: Parliament: House of Commons: Committee of Public Accounts and published by The Stationery Office. This book was released on 2009-06-18 with total page 44 pages. Available in PDF, EPUB and Kindle. Book excerpt: Agenda for Change, the pay modernisation programme for 1.1 million NHS staff in England, representing a pay bill of £28 billion in 2007-08, was implemented between December 2004 and December 2006. It covered all NHS staff, except doctors, dentists and senior managers. Agenda for Change introduced a job evaluation scheme and harmonised employment terms and conditions for the multitude of jobs within the NHS. A key part of the programme is a process for encouraging staff development and improving staff performance known as the Knowledge and Skills Framework. Agenda for Change was expected to bring about new ways of working which would contribute to improved patient care and to more efficient delivery of services. Total savings of £1.3 billion over the first five years were predicted. These were to come from improvements in productivity of 1.1 to 1.5 per cent a year, reductions in equal pay claims, reduced use of agency staff and more controllable pay costs. The Department and NHS Trusts did not establish ways of measuring the effects of Agenda for Change and there is no active benefits realisation plan. The NHS pay bill for the staff covered by Agenda for Change has risen by 5.2 per cent a year on average since 2004-05 while productivity fell by 2.5 per cent a year on average between 2001 and 2005. By autumn 2008 (nearly two years after Trusts had completed transferring staff to Agenda for Change terms and conditions and pay rates) only 54 per cent of staff had had a knowledge and skills review.
Download or read book DEFRA written by Great Britain: Parliament: House of Commons: Committee of Public Accounts and published by The Stationery Office. This book was released on 2009-07-07 with total page 40 pages. Available in PDF, EPUB and Kindle. Book excerpt: A Site of Special Scientific Interest (SSSI) is an area of land containing habitats and wildlife which are of national or international importance. There are over 4,000 SSSI sites in England, protected through restrictions on activities and development which would adversely affect the sites. In 2000, the Department agreed a Public Service Agreement (PSA) target to bring 95 per cent of SSSI land area into a 'favourable' or 'recovering' condition by December 2010. The reported condition of sites has increased from 52 per cent of land area in target condition in December 2002 to 86 per cent in February 2009. The programme of SSSI condition assessments is not up-to-date and Natural England has put in place a programme of work to address the backlog of assessments by 2010, and has introduced quality assurance systems and guidelines to improve the consistency of its record keeping. Public expenditure on SSSIs has more than doubled over the past eight years, from £35.6 million a year in 2000-01 to £85.4 million in 2008-09. Financial incentives to encourage private landowners to conserve sites account for some 58 per cent of public expenditure. There is scope to improve the processes for identifying new sites and declassifying existing ones which are no longer of special interest.
Download or read book Expert or Charlatan The Rise and Rise of Management Consulting written by and published by KW Publishers Pvt Ltd. This book was released on 2014-02-15 with total page 102 pages. Available in PDF, EPUB and Kindle. Book excerpt: The management consulting industry is a leading component of the world’s knowledge economy permeating every segment of industry, commerce and government service. A multi-billion dollar phenomenon, it has yielded its own body of knowledge and set of practices. Exponents do make a lot of money for the consulting businesses they serve. What is not always understood, or transparent, is the value clients receive. This book seeks to make good that deficiency in our perception of the profession. Learning on his deep and wide-ranging experience, Dr John Louth seeks to lift the lid on the management consulting profession in a critically reflective and accessible manner. With vignettes and examples drawn from his own experience and practice, he dissects the rational explanations usually provided by practitioners. He calls for restraint and self-awareness from both client and consultant, and advocates the reform of a profession that seems increasingly powerful and unregulated. Dr Louth explores the management consulting profession on its own terrain, through its own language and discourses. He disentangles the management consultant’s notions of “strategy,” “risk management,” “change” and “project management” so that these become meaningful to the layperson. Given the complexity that dominates the global geopolitical system and international economy, he asks how management consulting diagnoses can be effective in an uncertain and highly contingent world. With a foreword by Professor Rebecca Boden of the University of Roehampton Business School in London, this book is an accessible and scholarly monograph that is essential reading for those seeking to understand management consultancy and its role in the modern world.